Bridge Street Widening

The Bridge Street Widening Project aims to widen the section of roadway between Gray Avenue and Cooper Avenue to two lanes of traffic in each direction and add median, parkway, and pedestrian facilities to match adjacent improvements throughout the Bridge Street Corridor. This project will complete the four lane path of travel between State Route 99 and the City of Marysville, connecting City residents, commuters, and travelers with the vibrant businesses, schools, and homes along this important route. The City received $2.8 million in Local Partnership Program grant funding through the California Transportation Commission to go towards the funding of this project. For further information about the project, please contact the Engineering Division at (530) 822-4632 or [email protected].

Click on image to enlarge

Bridge Street Layout

Bridge Street Widening Project (Gray Ave to Cooper Ave) Schedule
Contract Bid Opening:
February 1, 2022 @ 2:00 PM
Contractor Award: March 1, 2022
Contractor Knife River:  Project Groundbreaking was held on May 13, 2022.  Knife River will start staging equipment and start initial pre-construction processes in May.   
Potential Traffic Impacts: Throughout the Project timeline
Construction Dates: May 23, 2022 to November 2023