| CDBG Sidewalk Improvements FY 09/10 |
| Contract: |
09-28 |
| Contractor: |
C & C Construction of Rocklin, CA |
| General Work Description: |
The work to be done consists in general of constructing ADA compliant curb, gutter, sidewalks, and access ramps at various locations throughout the City. |
| Potential Traffic Impacts: |
Minimal traffic impacts, roads will remain accessible during construction. |
| Construction Dates: |
March – May 2010 |
| Project Location Map: |
For easier navigation, open the full size CDBG Sidewalk Improvements FY 09/10 map. |