Completed Construction Project:

Rockholt Drainage Improvements
Contract: 11-11
Contractor: Franklin Construction of Chico, CA
General Work Description:  The project involves the reconstruction of Rockholt Way between Teegarden Avenue and South Colusa Frontage. Work includes earthwork, grading, asphalt concrete surfacing, aggregate base, concrete valley gutter, storm sewer improvements, and other items of work.
Potential Traffic Impacts: Closed to through traffic. Local residents will have access throughout construction.
Construction Dates: September – November 2012
Project Location Map: For easier navigation, open the full size map.

View Rockholt Drainage Improvements in a larger map