Project Overview/ Timeline

Overview

The process of replacing the 5th Street Bridge consists generally of preliminary engineering, environmental review, final design, and construction. Below is the status of several key tasks associated with each of these phases.

Phase 1 – Preliminary Engineering
  • Project Study Report (September 2010 – May 2013, Complete)
    • Develop Alternatives (Complete)
    • Public Workshops (Complete)
    • Engineering Studies (Complete)
  • Agency Coordination (Ongoing)
  • Geotechnical Soil Borings (Ongoing)
  • Detailed Topographic Survey (Ongoing)
  • Advanced Right of Way Planning (Ongoing)
Phase 2 Environmental Review
  • Environmental Technical Studies (Complete)
  • Draft Environmental Document Circulated (Complete)
  • Open House and Public Information Meeting (Complete)
  • Approve Preferred Project (Complete)
Phase 3 Final Design
  • Prepare Plans and Specifications (Spring 2016)
  • Advertise Project (Fall 2016)
  • Award Project (Late 2016)
Phase 4 Construction
  • Begin Work (Spring 2017)
  • Complete Bridge Replacement (Late 2018)